Project for the web limits and boundaries
-
Article
-
-
There are important limitations that you should know if you are using Project for the web. These limits apply to projects and tasks.
Project limitations
Field |
Limit |
Maximum total tasks for a project |
1000 |
Maximum total duration for a project |
3650 days (10 years) |
Maximum total resources for a project |
300 |
Maximum total links (successor only) for a project |
600 |
Maximum total custom fields for a project |
10 |
Task limitations
Field |
Limit |
Maximum hierarchy level |
10 levels |
Maximum links (successor + predecessor) |
20 |
Maximum duration of leaf task |
1250 days |
Maximum duration of a summary task |
3650 days (10 years) |
Maximum resources assigned to a task |
20 resources |
Supported date range for a task |
1/1/2000 - 12/31/2149 |